Victoria · Geelong, the Bellarine and the Surf Coast

You bought a pool. Here is the rest of it.

Your contract delivers a pool. Six trades, four legal duties and one order of work are yours, and nobody in the process is required to tell you what they are. This is that list, checked against the law rather than remembered.

Every regulatory fact on this page was checked against its source on 10 September 2026. Fees and penalties in Victoria change on 1 July each year. If you are reading this after 30 June 2027, check the figures.

Section one

What your pool contract does not cover

Most people find this out in week three, standing in a yard that is now a hole, holding a contract that stops at the water's edge.

Your builder delivers a pool. In most contracts that means the excavation, the shell, the plant and the water, and a defined scope around it. It is a good contract. It is just a smaller contract than the job.

Six trades commonly sit outside it. Not always the same six, and not always all six, which is exactly why the first thing to do is read your own scope of works and mark what is missing. But this is the usual shape of the gap.

Before the shell
Electrician

Earth bonding back to the house switchboard, dedicated circuits for the equipment, and a safety certificate at the end. Pool electrical work is its own thing and it happens early.

Before water goes in
Fencing

The barrier, permanent or temporary. This is the one with the law attached, and the one that decides where your paving can go.

With the shell
Plumber

Backwash and overflow to a legal discharge point, and any water supply run. Often assumed to be in the pool contract. Often is not.

After the shell
Tiler

Waterline tile, coping and the surround, if your contract stops at a bare shell. Check whether coping is in or out. It is the most common surprise.

After the barrier
Landscaper

Paving, levels, drainage, planting and retaining. Levels are not a finishing decision. They change whether your fence passes.

Throughout
Rubbish removal

Spoil from the dig, offcuts, packaging, broken paving. It accumulates from day one and it is nobody's job unless you make it someone's job.

The thing to do today
Get the scope of works out. Read down the exclusions, not the inclusions. Write the six words above in the margin and tick the ones your builder has, in writing, agreed to do. Whatever is left unticked is a phone call you are going to make, and the order you make them in is section three.
Section two

The four things the law makes you do, and when

These are yours, not your builder's. They sit in the Building Regulations 2018 and they do not move because the job ran late.

What follows is the sequence for a pool being built now, meaning one where the building permit was issued on or after 1 November 2020, or was issued earlier but construction did not start until after that date. Older pools run on a different and now largely expired set of dates, so if yours is an existing pool this is not your page.

1Your building surveyor inspects the barrier and issues the certificate
At final inspection

The last of the mandatory inspections under your building permit is the final one, on completion of the pool and its barrier. If your building surveyor is satisfied the barrier meets the standard, the surveyor issues you a certificate of pool and spa barrier compliance, which is a Form 23.

This surprises people, so it is worth saying plainly: for a brand new pool you do not go and hire a separate pool inspector for the first certificate. It comes from the building surveyor already attached to your permit. You start hiring your own inspector at the four year mark, in duty four.

Building Regulations 2018, regs 169(d) and 147Y.

2Register with council, and lodge the Form 23 at the same time
Within 30 days

You apply to your council to register the pool, and you lodge the Form 23 with that same application. They are one act, not two. Doing the registration now and the certificate later is the common mistake, and it is an offence in its own right.

The 30 days runs from the day you receive your occupancy permit or certificate of final inspection, not the day it was issued or dated. If it sat in a builder's tray for a fortnight, your clock started when it reached you. Keep the email.

Building Regulations 2018, reg 147M.

3Council writes back, and that letter sets your next date
You wait for this one

Once registered, council must notify you in writing of five things: that the pool is registered; the date of construction it has determined; the barrier standard that applies to your pool; that you can appeal that construction date to the Building Appeals Board within 30 days; and the date your next certificate is due.

Do not file this and forget it. It is the only document that tells you, in writing, which standard your fence is judged against for the life of the pool. Scan it. The next date is four years from the day your first certificate was lodged, not from the day it was issued and not from the day you swam.

Building Regulations 2018, regs 147R(1) and 147R(3).

4From here on, you arrange the inspection yourself
Every four years

Council does not inspect your barrier and council does not endorse or recommend anyone. Greater Geelong, Surf Coast and Queenscliffe all say so on their own pages. You engage a registered inspector, you get a fresh Form 23, and you lodge it with council by the date in that letter.

One trap. The certificate you lodge must be dated no more than 30 days before the day you lodge it. So do not get the inspection done nice and early, put the certificate in a drawer, and lodge it on the due date. That certificate will be too old and you will be paying for a second inspection.

Building Regulations 2018, regs 147V(1) and 147V(2).

If you miss one

Failing to register, and failing to lodge a certificate on time, are separate offences. In practice they arrive as a building infringement notice, an on-the-spot fine currently a bit over four hundred dollars. If a council took it to court instead, the maximum is roughly five times that.

The barrier itself is a different order of thing. Failing to keep your barrier properly maintained carries a maximum around five times higher again, and it cannot be settled with an on-the-spot fine at all: it is not on the list of offences a council can issue an infringement for. It can only be prosecuted.

About the big number
You will see a five figure sum quoted around pool compliance, usually attached to paperwork. It is not a paperwork fine. It is the theoretical maximum a court could impose for failing to maintain a barrier, and no council issues it for a late lodgement. Anyone who quotes it at you to sell you something is either careless or hoping you will not check. The honest answer is the one above.
Section three

The order things have to happen in

This is the part nobody writes down, and it is where the money is lost. Not in the price of the paving, in the second time you pay for it.

The permit has two clocks, and they are not the ones you think

Clock one · 12 months
Work must start within 12 months of the permit being issued

Signing a contract is not starting work. If your builder's schedule pushes the dig out, this is the date to watch.

Clock two · 6 months
A standalone pool must be finished within 6 months of starting

Six months is short, and it is the one that catches people. But it applies only where the pool is the only building work. If the pool is going in at the same time as other building work on the same block, the pool runs to that other work's period instead, which for a house or a Class 10 structure is longer.

The trap in clock two
Concurrently means concurrently

Holding a permit for a verandah you built two years ago does not extend anything. The work has to be running at the same time on the same allotment. If you are going to be tight, ask your building surveyor for an extension before the date passes, not after. Failing that, the Building Appeals Board.

Why the fence sometimes comes before the paving, and sometimes after

People treat the fence as a finishing job and the paving as a finishing job, and then argue about which looks better first. That is not the question. The question is levels.

Barrier height is measured from ground level on the approach side, the outside. Paving changes ground level. Lay paving on the outside of a compliant fence and you can lift the ground enough to turn a barrier that passed into one that fails, without anyone touching the fence.

Then there is the clear zone. Outside the fence, a 900mm band has to stay free of anything climbable. Inside, 300mm. That band is where retaining walls, garden beds, pumps, pots, furniture and young trees all want to go, and it is the single most common reason a barrier fails on a job that is otherwise finished.

The rule that saves the money
Set the fence line and the finished levels together, on paper, before either trade starts. Not the fence design, the fence line, and the finished height of every surface within a metre of it. If the landscaper and the fencer have never seen each other's drawing, you are the one paying to lift the paving.

And a barrier has to exist before the pool holds water

The barrier rules apply to anything capable of holding more than 300mm of water. That means a temporary barrier goes up as soon as the shell can hold water, not when the landscaping is done. Ask your builder whose job the temporary fence is, in writing, because it is frequently nobody's.

What the inspector will fail you on

Some failures give you time to fix them. Three do not.

Where any of these are found, the inspector must immediately issue a certificate of non-compliance. There is no 60 day grace period and no negotiation.

  • A gate or door in the barrier that can be opened by someone who cannot reach the opening mechanism. In plain terms, a child can open it.
  • A gate or door that cannot be completely closed. Dropped hinges, a dragging latch, a gate that rests against the post.
  • Any part of the barrier less than 1 metre high, measured from ground level on the approach side.

Building Regulations 2018, reg 147ZF.

What your builder needs from you, and when

Every decision below is cheap while it is on paper and expensive once it is in the ground. They come at you faster than you expect, usually as a text message asking for an answer today.

  • Before the dig: access route for the machine, where the spoil goes, where the equipment sits, and where the fence line runs.
  • Before the shell: the electrician's requirements back to the switchboard, and the discharge point for backwash.
  • Before the coping: coping and waterline tile selection, and whether they are in or out of your contract.
  • Before the paving: finished levels within a metre of the barrier, agreed with whoever is building the barrier.
  • Before handover: confirmation of who is arranging the final inspection with the building surveyor, and when.
Section four

What it costs

Ranges only, and only for the parts with a published price. Trade prices are not here because they move too much to be useful, and a number that is wrong is worse than no number.

Council fees

Here is something worth knowing, because it explains why the numbers you find online disagree with each other. Councils set these fees, but the Building Regulations cap them, in fee units. The cap moves every 1 July when the fee unit is re-indexed. Most councils simply charge the cap, which is why the figures match when they are current and differ when one page has gone stale.

The fee unit for 2026-27 is $17.27. Councils may charge less than the cap. They may not charge more.
FeeRegCapMaximum 2026-27Greater GeelongSurf CoastQueenscliffe
Registering the pool, one off147P(2)2.15 fee units$37.13$37.10to confirmto confirm
Lodging a Form 23 certificate of barrier compliance147X(2)1.38 fee units$23.83$23.80to confirmto confirm
Information search, older pools only147P(3)3.19 fee units$55.09$55.10to confirmto confirm
Lodging a certificate of barrier non-compliance147ZJ(2)26 fee units$449.02$449.10to confirmto confirm

Greater Geelong's figures come from its own Building Services Fees page, which states they apply to the 2026-27 financial year. Surf Coast and Queenscliffe are marked to confirm rather than filled in from a published page, because neither states a fee year we could verify. We will fill them in once we have confirmed them with the council directly.

Two notes on that table

The information search fee applies only to pools built before 1 November 2020, where council has to go looking for the records. If you are building now, it does not apply to you.

Registration is a one-off. The lodgement fee comes round with every certificate, so once now and once every four years.

The barrier inspection, at the four year mark

Inspectors who state they cover Geelong, the Bellarine and the Surf Coast are publishing $250 to $330 for a standard Form 23 inspection, clustering around $280 to $300. That is what was on their own websites on 10 September 2026.

Two things move the real number, and neither is in the headline price.

  • Re-inspection. Some include it free. Most charge for it, between $110 and $190. Barriers fail first time often enough that this is not a footnote: the cheapest headline price can end up the dearest total.
  • GST. Only a minority say whether their price includes it. "All inclusive" is not a statement about GST. Ask.

Nobody's price includes lodging the certificate with council. That is yours to do, it takes about ten minutes, and it keeps the certificate in your name.

Section five

What to ask your builder before the dig

Tick them off as you go. Ask for the answers in an email afterwards, because an answer you cannot find later is not an answer.

Scope
The permit and the clock
The barrier
Handover
0 of 17 asked. Ticks are yours alone: nothing here is saved or sent.
Section six

Who to ring

Three councils cover this region. The Bellarine is not one of them: it sits inside Greater Geelong, apart from Queenscliff and Point Lonsdale, which are the Borough of Queenscliffe.

City of Greater Geelong
03 5272 5272

Geelong and most of the Bellarine, including Ocean Grove, Barwon Heads, Drysdale, Portarlington and Clifton Springs.

pools@geelongcity.vic.gov.au
Surf Coast Shire
03 5261 0600

Torquay, Jan Juc, Anglesea, Aireys Inlet and Lorne, and inland to Winchelsea and Deans Marsh.

info@surfcoast.vic.gov.au
Borough of Queenscliffe
03 5258 1377

Queenscliff and Point Lonsdale only. A separate council with its own register and its own portal.

info@queenscliffe.vic.gov.au
Building and Plumbing Commission
bpc.vic.gov.au

The state regulator, and where Form 23 and the barrier self-assessment checklists come from. It replaced the Victorian Building Authority, so old vba.vic.gov.au links now redirect.

Your building surveyor
Ask your builder

The single most useful number you do not currently have. They issue your permit, run the mandatory inspections, issue your first Form 23 and can grant an extension of time.

A registered pool inspector
At year four

You choose and engage them yourself. Council does not inspect and does not endorse anyone. Ask about re-inspection cost and GST before you book.

And us

Poolside Partners is an independent adviser to new pool owners in Geelong, the Bellarine and the Surf Coast. We do not hire trades, sign contracts or hold your money: every contract stays yours. What we sell is the sequence. What is coming, in what order, what is due, and someone to ring who has watched it run before.

If this page was useful and you would rather have it mapped against your own contract and your own dates, that conversation is an hour at your kitchen table and it costs nothing. You keep the notes either way.

Tell us where you're up to

This guide is general information about Victorian requirements, not legal advice and not a substitute for your building surveyor. Your council's registration letter is the document that confirms which barrier standard applies to your pool. Fees and penalty amounts change on 1 July each year.

Poolside Partners

We tell new pool owners what is coming, in what order, and what is due, from signed contract to first swim. You hold every contract.

A.B.N. 73 521 325 586

SERVICE AREA

Geelong · Surf Coast · Bellarine